MODELING OF SCHEDULE DELAY AND COST
OVERRUN IN EDUCATIONAL BUILDINGS
PROJECTS IN EGYPT
المؤلف
Mohamed,Mohamed Gebrel Ali
هيئة الاعداد
باحث / محمد جبريل على محمد
مشرف / كمال عباس عساف
مشرف / معتز عوض فرج
مناقش / يحيي عبد العظيم حسانين
مناقش / أحمد محمد عبد العليم
الموضوع
educational buildings
تاريخ النشر
2022
عدد الصفحات
120 p.
اللغة
الإنجليزية
الدرجة
ماجستير
التخصص
الهندسة المدنية والإنشائية
الناشر
تاريخ الإجازة
24/2/2022
مكان الإجازة
جامعة أسيوط - كلية الهندسة - الهندسة المدنية
الفهرس
Only 14 pages are availabe for public view

from 172

from 172

Abstract

The construction industry is one of Egypt’s most significant industries. The
majority of construction projects are known to have time delays and cost
overruns. The research main objective is to identify the most significant causes
of schedule delay and cost overrun in educational building projects in Egypt. This
objective was accomplished by means of an extensive literature review and a
questionnaire-based survey for the purpose of evaluating the perceptions of the
key stakeholders participated in the construction of educational building projects.
The questionnaire was divided into three sections; the main section concentrated
on the causes of delay and cost overrun in construction projects, the other sections
focused on general information about respondents and the effects of delay on
construction projects. The forty causes of delay and cost overrun gathered
through the literature review were categorized into seven groups. Responses were
gathered from 130 participants representing the key stakeholders participated in
the project’s construction. The analysis was conducted to determine the amount
of delay and cost overrun experienced by the projects, in addition to the indices
concerning the frequency of occurrence, impact on time and cost, and
significance of the seven groups. As well, a ranking of the forty causes was
performed to identify the most critical causes of delay and cost overrun.
Concluded that the most crucial causes affecting the delay and cost overrun in the
educational building projects in Egypt are: Price instability, Price escalation of
material, delays in contractors progress payment, financial problems, contractor’s
difficulties in financing the project.